Insurer: Governance and KPI Framework.

An insurance company with a national branch network had already awarded an IFM contract worth roughly €2.5M a year that it couldn’t govern: the reporting was produced entirely by the supplier, and a penalty had never once been applied. The brief was to put governance and KPIs in place on an IFM contract already under way: a scorecard, committees and independent reporting.

Project snapshot 
SectorInsurance, national branch network
Contract value~€2.5M/year, IFM already awarded
My roleIndependent consultant
PhasesContract diagnosis · KPI scorecard · committees · reporting · handover

The starting point

There was no award problem here. The tender had already happened, the supplier was operating, and the service wasn’t bad. The problem was something else, and it’s far more common than it looks: the contract couldn’t be governed.

Monthly meetings had turned into a review of loose incidents. The report arrived late, was produced start to finish by the supplier, and nobody had an independent source to check it against. Penalties were written into the contract and had never once been applied, which in practice made them purely decorative.

What the diagnosis uncovered

  • The contract had indicators, but no written calculation formula. Every month the result got argued over instead of acted on.
  • Every indicator’s data was generated exclusively by the supplier, with no client access to the management system.
  • A single monthly meeting mixed operational and strategic matters. Urgency always crowded out the deeper conversation, and the contract review got pushed back indefinitely.
  • There were no minutes recording agreements, owners and dates, so nothing discussed was enforceable three months later.

The decisions that changed the outcome

Cut before adding. The first move wasn’t creating new indicators, but keeping the few that could actually trigger a consequence and giving them a formula, a threshold and an owner. A short scorecard that gets applied is worth more than a long one nobody looks at.

Getting an independent data source. Read-only access to the supplier’s management system was negotiated. That single change made the reporting verifiable, and with it the monthly conversation stopped depending on good faith.

Separating the three committee tiers. Operational for incidents, tactical for indicators and spend, strategic for trends, penalties and renewal. Each with a fixed agenda and minutes recording agreements, owners and dates.

Framing it as rules for both sides. The framework also captured the client’s own failures to deliver — access that never arrived, decisions that dragged on — because they’re a real cause of much of the delay, and because that’s what makes a supplier accept the system instead of defending itself against it.

The result

The contract went from being discussed by impression to being discussed by data. With the scorecard running and minutes as the record, difficult conversations stopped depending on the personal relationship with whoever happened to be the account manager, and started resting on the signed document instead.

And there was an effect that wasn’t part of the brief: the supplier started bringing problems to committee that it used to hide, because the framework gave it a place to raise them with its own data on the table.

What I took from this project

That most contracts that “don’t work” don’t have a supplier problem — they have a control architecture problem. Before considering a change of supplier, with its full transition cost, it’s worth checking whether the current contract even allows for measuring and enforcing anything. In quite a few cases, it doesn’t.

More on this on the contract governance page. The other two case studies are on the case studies page.

Case study published without identifying the client, for confidentiality. The figures are real; the scope is described in as much detail as the agreement allows.