A distribution company with more than 220 service locations across Spain had its services contracted zone by zone, with no common scope and no defined service level. The brief was to design the model, write the technical and commercial specification, and support the tender for an IFM contract. Result: an IFM contract worth roughly €1.5M a year, with a consistent scope and measurement in place from the first month.
| Project snapshot | |
|---|---|
| Sector | Distribution, national network |
| Scope | More than 220 service locations across Spain |
| Contract value | ~€1.5M/year |
| My role | Independent consultant |
| Phases | Diagnosis · operating model · specifications · tender · award · mobilization |
The starting point
The network had grown through successive openings, and each zone had sorted out its services however it could: a maintenance supplier inherited here, cleaning contracted by the store manager there, and at some sites agreements that weren’t written down anywhere at all.
The symptom they arrived with wasn’t cost. It was that nobody could answer two questions from senior management: what does this cost in total, and what do we get in return. The first could be reconstructed with effort. The second had no possible answer, because no written service level existed to compare anything against.
What the diagnosis uncovered
- Actual spend was spread across dozens of suppliers and several accounting lines, so the aggregate figure the company worked with didn’t match actual spend.
- Comparable sites had very different service levels with no operational reason behind it — only the history of who had contracted what, and when.
- Corrective maintenance was handled through direct calls from each site, with no shared record. There was no way to know which assets failed most often or what each breakdown cost.
- Internal time spent coordinating suppliers was the model’s highest invisible cost, and it never showed up on any invoice.
The decisions that changed the outcome
Standardize before tendering. The temptation was to tender what already existed, zone by zone, and keep the lowest price in each. That would have produced incomparable bids and the same disorder under different names. A standard scope was defined first by site type, with exceptions justified in writing.
Publish the baseline data. Every bidder received the site inventory with floor areas, operating hours and criticality, plus the available intervention history, gaps acknowledged. That’s what makes bids comparable: if every company estimates volume its own way, you’re comparing their optimism, not their price.
A single unit of measurement. Price per site per month by type, plus a fixed unit-price table for anything falling outside scope. That second part is where what’s given up in the first gets recovered, which is why it was scored in the award.
Service levels with a formula. Every indicator left the specification with its data source, its formula, its threshold and its financial consequence. None of them were written in prose.
How it was executed
- Diagnosis and inventory. Reconstructing actual spend by site and service, and surveying assets and floor areas.
- Target operating model. Standard scope by site type, deciding what got integrated and what stayed separate, and a governance structure.
- Technical and commercial specification. Requirements, service levels, penalty regime, pricing structure and evaluation matrix.
- Tender. Pre-selecting suppliers with real capability across the whole geography, a shared question round, comparative analysis and a reasoned recommendation.
- Mobilization. A first-90-days plan with contractual milestones, so the value of the tender wasn’t lost in the transition.
The result
An IFM contract worth roughly €1.5M a year, with the same scope defined across the whole network, a KPI scorecard operational from the first month, and a single point of accountability for the whole thing. The company went from managing dozens of supplier relationships to managing one contract.
The least visible and most important change: for the first time, a baseline existed. From there you can negotiate, compare and enforce; before, any conversation about the service was a debate about impressions.
What I took from this project
That in highly scattered networks, standardization is worth more than direct savings. The price per site may barely drop, and the project still pays for itself through the internal time no longer spent and the ability to detect where the service is failing — something that simply didn’t exist before.
More on this on the tender and bid advisory page. The other two case studies are on the case studies page.
Case study published without identifying the client, for confidentiality. The figures are real; the scope is described in as much detail as the agreement allows.