A retail company in expansion needed a replicable services model to open sites in three countries without multiplying its internal management structure. A €2.5M scaled IFM model was designed, validated in a 3-site pilot, and rolled out in waves up to 85 sites, with the same KPI scorecard across all three countries.
| Project snapshot | |
|---|---|
| Sector | Retail, in expansion |
| Final scope | 85 sites across 3 countries |
| Contract value | €2.5M |
| My role | Project led during my executive career |
| Phases | Model · supplier selection · 3-site pilot · review · phased rollout |
The starting point
The pace of new openings made the obvious alternative unworkable: negotiating service by service in every country and every site. Every opening would have consumed weeks of internal work and produced different conditions at equivalent sites.
What was needed wasn’t a contract — it was a replicable model: a standard scope per site, a known cost before opening, and a way of measuring the service that meant the same thing in all three countries.
The decisions that changed the outcome
Pilot before rollout. It started with three representative sites — neither the best nor the worst — with a KPI scorecard from day one. The pilot’s stated goal wasn’t for it to go well: it was to find out what would break before multiplying it by eighty-five.
Verify real capability in each country. An international supplier’s stated presence and its actual capability in each location aren’t the same thing, especially once it subcontracts. This was checked country by country before awarding.
A single KPI scorecard. Same indicator, same formula, same threshold in all three countries. An indicator calculated differently at each site lets you compare nothing, and without comparison there’s no replicable model.
Phased rollout, not all at once. By geography and site type, with a validation milestone between waves. Slower on paper; far cheaper in incidents and renegotiation.
What the pilot taught
Three scope decisions that looked reasonable on paper turned out to be wrong once measured, and were corrected before rollout. That’s the entire value of a pilot: three mistakes fixed across three sites instead of replicated across eighty-five.
Operating across several countries also changes four things worth deciding before signing: each country’s labor and subrogation framework, the tax and invoicing structure, the supplier’s real capability in each location, and the language and time zone of the reporting.
The result
A €2.5M IFM model operating across 85 sites and three countries, with the same KPI scorecard everywhere and a known cost per site before every opening. The internal management structure didn’t grow at the same pace as the network — which was exactly the project’s goal.
What I took from this project
That the expensive mistake in an international rollout is almost never the price: it’s replicating at scale a scope decision nobody validated with data. A short, well-measured pilot costs a few weeks and avoids four years of a badly sized contract.
More on this on the IFM model design and scaling page. The other two case studies are on the case studies page.
Case study published without identifying the client, for confidentiality. The figures are real; the scope is described in as much detail as the agreement allows.