How to audit a Facility Management contract: a six-dimension method

Auditing a Facility Management contract means putting three things side by side that rarely match: what was signed, what is being invoiced and what is actually delivered. In my method, every finding is assigned to one of six dimensions (scope, price, service, control, risk and governance) and prioritised by its financial impact, not by the number of complaints it generates.

When is it worth auditing an FM contract?

There are seven warning signs. With three or more, an audit usually pays for itself through what it finds:

  • Nobody has reviewed the contract in depth since it was signed three or more years ago.
  • The monthly invoice changes from one month to the next and nobody on your team can explain exactly why.
  • Out-of-scope work invoiced on top of the contract exceeds roughly 15–20% of the base contract value (a rule of thumb, not a benchmark).
  • Not a single service credit or penalty has ever been applied, not even in months of clearly poor service.
  • All performance information comes from the provider, and you have no data of your own to check it against.
  • The price has been indexed every year (in Spain, usually to the CPI) without anyone checking whether the scope was still the same.
  • You do not know what the service costs you per square metre or per site, or you have nothing to compare it with.

The best moment is six to twelve months before the contract expires. The audit findings are exactly the raw material for the next technical specification, so auditing before re-tendering is the most cost-effective sequence in this kind of work. If the conclusion is that you need a new provider, the steps are in how to re-tender and prepare the exit of your current provider.

What documentation do you need to start?

Five things, and the client organisation already holds all of them. You do not need to ask the provider for anything during the findings phase:

  1. The signed contract and its annexes: specification, awarded bid, price schedule and any later amendments.
  2. The last twelve months of invoices, with the detail of out-of-scope work.
  3. The performance and KPI reports the provider has delivered over the same period.
  4. Minutes of the contract review meetings and the record of service credits applied, if there is one.
  5. The current inventory of sites, floor areas, occupancy and critical equipment, to check it against the contracted scope.

What do you review in each of the six dimensions?

With that documentation on the table, each finding is assigned to one of six dimensions. The order matters less than covering all of them, because the cause of a problem in one dimension often sits in another.

1. Scope

Does what you are buying match what the organisation needs today? The classic mismatches: services still being paid for at sites that have closed, cleaning frequencies designed for pre-hybrid occupancy, planned maintenance on equipment that no longer exists and, the other way round, critical services nobody ever contracted that end up being solved every month as out-of-scope work.

2. Price

Two different questions. The external one: is the price in line with the market? The internal one, which is often overlooked and usually recovers more money: is the price consistent with itself? Typical examples are the same service with different unit rates by region and no operational reason, overtime billed at rates that do not appear in the contract, or an annual indexation applied to the whole price when the contract limited it to the labour component.

3. Service

Are the committed service levels being met and, above all, what data proves it? What matters here is not the compliance percentage in the monthly report, but where that number comes from and who produces it. How each indicator should be built is covered in how to design the KPIs of a Facility Management contract.

4. Control

Can the client measure with its own sources and enforce with consequences? A contract with perfectly drafted service credits but no independent data to trigger them has, in practice, no control at all.

5. Risk

Dependency on the provider, reversibility, ownership of the CMMS data, regulatory and labour compliance, and coverage of statutory maintenance obligations. It is the dimension that gets the least attention and the one that costs the most when it fails.

6. Governance

Review meetings that actually take place, minutes with agreed actions and owners, decisions that can be traced. Without this, any improvement that comes out of the audit unravels within six months. This is the part addressed by an FM contract governance model.

DimensionQuestion it answersTypical evidence
ScopeAre we buying what we need?Inventory versus contracted scope
PriceAre we paying what it is worth, consistently?Invoices versus price schedule
ServiceAre we getting what was committed?KPIs versus actual incidents
ControlCan we measure and enforce?Source of the data and service credits applied
RiskWhat happens if this breaks?Exit clauses and statutory obligations
GovernanceWho decides, and with what information?Minutes, attendees and closed actions

What does an FM contract audit usually recover?

It depends almost entirely on how old the contract is and whether anyone has been monitoring it. In contracts that have run for several years without review, findings typically combine invoicing corrections, scope adjustments and price rebalancing. In recent, well-governed contracts, the findings tend to be about service rather than cost. Any figure quoted before looking at the documentation is a guess.

Always separate two types of saving, because they are worth different things: recurring savings, which reduce every invoice from then on, and one-off recoveries, which is money already overbilled that you get back once. The second looks more impressive in the report; the first is the one that changes next year’s budget.

Should the provider know you are auditing the contract?

That is the client’s decision, and both options are defensible. My usual recommendation is to run the findings phase with the client’s own documentation and sit down with the provider afterwards, with the data already checked. Not out of mistrust, but as a matter of method: a conversation based on quantified findings takes an hour, while the same conversation based on suspicions can drag on for three months.

The other side needs saying too, because it happens often: in many audits the outcome is that the provider is complying, and the problem is a contract that does not allow you to measure or enforce anything. That finding is also worth money, because it prevents an expensive and pointless change of provider.

What to do on Monday morning

Without hiring anyone and in about an hour, you can run the short version of the price dimension: take the last twelve invoices, separate the fixed amount from the variable amount and calculate what percentage out-of-scope work represents over the base contract. If it is above 20%, the contracted scope is not the real scope, and there is a conversation to be had. To work through the six dimensions one by one afterwards, use the FM contract audit checklist, with 48 points.

Frequently asked questions

How often should a Facility Management contract be audited?

An in-depth review every two to three years, and always one six to twelve months before expiry, so the findings feed the next specification. In contracts with active governance (review meetings, measured KPIs and independently checked reporting), a formal audit is less urgent, because much of that control is already happening continuously.

Can the company that operates the contract audit it?

It can, but the report will have a structural limit: no company documents in detail where it is overbilling a client. It is not a question of the team’s professionalism, it is a question of incentives. The same applies to the consulting arm of the provider’s own group. Who on the client side should own this review is covered in which team should stay in-house when you outsource FM.

What is the difference between auditing a contract and renegotiating it?

The audit produces evidence: what is not being complied with, what is being overpaid and what each item is worth. Renegotiation is what you do afterwards with that evidence. Renegotiating without auditing first means negotiating blind against someone who does have the data.

If you want the full method, it is on the Facility Management contract audit page, and if you would rather look at it together, thirty minutes is enough to know whether there is work to do.

Hugo Gómez Crespo

Hugo Gómez Crespo

Consultor independiente de Facility Management. 16 años dentro de los grandes proveedores de IFM; hoy, al servicio de quien contrata. Miembro de IFMA España desde 2014. Trayectoria completa · LinkedIn.

Hablemos

Una conversación de 30 minutos, sin coste y sin propuesta comercial detrás, suele bastar para saber si merece la pena seguir hablando.

Hablemos