How to write the technical specification for a Facility Management contract

The technical specification of a Facility Management contract defines what you are buying and how it will be measured. It needs nine components: baseline data, scope by service, service levels with their formula, the penalty regime, reporting obligations, the transition plan, systems and data requirements, exit conditions and award criteria. If any of them is missing, the bids you receive will not be comparable with one another.

What data should bidders get before anything else?

This is the section that prevents the most inflated bids, and the one that is most often neglected. If every bidder has to estimate the workload on their own, each one estimates differently and comparing their prices stops meaning anything.

  • A list of sites with floor area, use, opening hours and criticality. If the network will change during the contract, also ask for unit prices by site type: see adding and removing sites in a multi-site FM contract.
  • An inventory of the main assets, with age and condition where known.
  • The incident history for the last 12–24 months, even if it is imperfect.
  • Real volumes and consumption: cleaning area, number of call-outs, on-site hours.
  • Details of any staff who will transfer to the new provider: role, length of service and applicable collective agreement.
  • What is not working today. Publishing it is not a weakness: it is what allows bidders to propose solutions instead of repeating the previous contract.

On staff transfer it pays to be precise. In Spain, for most FM services the obligation to take over the existing workforce (known as subrogación) comes from the applicable sector collective agreement, not from the specification; other countries have their own rules. Either way, the client’s responsibility is to provide complete, up-to-date employment information. If that information turns out to be wrong, the extra cost ends up being claimed back, and rightly so.

How do you define the scope without leaving gaps?

Service by service, and for each one three things: what is included, what is not, and who pays for what falls outside. The third is the one that prevents next year’s arguments. If the specification is going to bundle every service into a single integrated contract, decide first whether that model suits your organisation: I explain the trade-offs on the IFM model page.

The four places where there are almost always cracks:

  1. The line between reactive repair and improvement. Replacing a faulty light fitting versus switching the fitting to LED. Without a written criterion (by amount, by nature or both), everything tends to end up being paid by the client.
  2. Supplies and consumables. Who buys them, at what price and with what mark-up.
  3. Managing third parties. Lifts, fire protection, installations still under warranty: if the provider coordinates them, the specification must say whether it is accountable for them or only calls them out.
  4. Minor works. Set the threshold in euros above which a job stops being an out-of-scope request and becomes a separate project.

How do you write service levels that can be enforced?

Every service level needs the same anatomy as a KPI: data source, formula, target threshold, penalty threshold, owner and exclusions. The detail is in the guide on how to design the KPIs of an FM contract.

The most common mistake is writing the service level as prose: “a rapid response to critical incidents will be guaranteed”. That cannot be measured, cannot be penalised and, in a public tender, cannot be scored without arbitrariness either. The enforceable version states what a critical incident is, how quickly it must be answered, when the clock starts and what happens if the target is missed.

How do you structure pricing so that bids are comparable?

DecisionUsual optionWhat to watch
Unit of measurePrice per site per month, or per m² per monthPublish the baseline figure for everyone: if each bidder calculates its own floor area, no comparison is possible
StructureFixed monthly fee + reactive maintenance budget + unit ratesThe budget needs a settlement rule: unspent amounts are refunded or carried over, but the specification says which
Out of scopeClosed schedule of unit ratesAsk for it in the bid and score it; it is where providers recover what they give away on the fixed price
Price reviewIndex and pass-through percentageLimit indexation to the labour component, not the whole contract value
Management feeExplicit and separateIf it is hidden inside the rates, it cannot be negotiated at renewal

What should you require on systems and data?

This is the newest part of an FM specification and the one that does most to prevent lock-in four years down the line. Three requirements are enough: the client has read access to the CMMS throughout the life of the contract; the data (assets, maintenance history, consumption) belongs to the client and can be exported in a usable format; and handing that information over at the end of the contract is an obligation with a deadline, not a favour.

And the award criteria?

In a services contract with real operational demands, a reasonable split is around 50–60% technical and 40–50% price. But the split matters less than this: if the technical part is scored with criteria so generic that every bidder gets practically the same mark, the real weight of price is 100%.

In Spain’s public sector there is also a legal distinction between criteria assessed by formula and criteria subject to value judgement, with rules in Law 9/2017 on Public Sector Contracts on how they are weighted and the order in which envelopes are opened. In the private sector none of this is mandatory, which is precisely why it is worth copying the discipline: criteria written down before bids are opened, and a traceable decision. How those criteria are then applied, normalising before scoring, is covered in how to evaluate Facility Management bids.

What to do on Monday morning

Take the specification you are preparing and look for one thing only: how many of your service levels have a written calculation formula. If the answer is none or almost none, that specification is not ready to go out, however advanced it may look.

The costliest mistakes in an FM specification, one by one, are on the FM tender advisory page, and a complete process is described in the national distribution IFM tender case study. If you are re-tendering because the current contract is not working, read changing your Facility Management provider first. And if your specification is already written, send it to me and I will tell you the three things I would change.

Hugo Gómez Crespo

Hugo Gómez Crespo

Consultor independiente de Facility Management. 16 años dentro de los grandes proveedores de IFM; hoy, al servicio de quien contrata. Miembro de IFMA España desde 2014. Trayectoria completa · LinkedIn.

Hablemos

Una conversación de 30 minutos, sin coste y sin propuesta comercial detrás, suele bastar para saber si merece la pena seguir hablando.

Hablemos