Changing Facility Management provider goes well when the decision is made with data and the incumbent’s exit is prepared before the tender, not after the award. First decide whether to renew, renegotiate or re-tender; then check what the current contract allows (extensions, notice period, exit obligations); and finally set down in writing what information the outgoing provider must hand over and in what format. What is not requested before the tender rarely arrives in time for go-live.
Renew, renegotiate or re-tender?
When an FM contract approaches expiry and the service is not convincing, the usual reaction is to go to tender. It is not always the best option: a tender takes internal time, creates a period of uncertainty for the incumbent and, if another provider wins, forces a mobilisation. Before deciding, separate two questions: is the problem the provider or the contract? It is also worth ruling out a third cause: a provider that is losing money on the contract and has quietly stopped investing in it (see why your FM provider has to make money).
| Situation | Option that usually makes sense |
|---|---|
| The provider delivers, but the contract does not allow you to measure or enforce | Renegotiate: rework scope, KPIs and governance with the same provider |
| Service is reasonable, but the price has not been tested against the market for years | Re-tender, allowing the incumbent to bid |
| Repeated, documented failures with no credible improvement plan | Re-tender and prepare the exit |
| Scope has changed a lot (sites, occupancy, services) | Re-tender: the current contract no longer describes the need |
| Change of model (from multi-vendor to IFM or vice versa) | Re-tender with a new specification |
To answer with data rather than impressions, the starting point is an audit of the current contract (the method is set out in how to audit a Facility Management contract): what was signed, what is invoiced and what is actually delivered. Often the finding is that the provider does what the contract asks and the problem lies in what the contract does not ask. In that case, changing provider without changing the contract reproduces the problem under a different name.
What to check in the current contract before deciding
Six clauses define your room for manoeuvre. Read them before announcing anything to the provider:
- Term and extensions. If the extension is automatic, there is a date after which the contract renews itself.
- Notice period. Deadline and form for giving notice of non-renewal. This is the date that drives the rest of the timeline.
- Exit obligations. Whether the contract obliges the provider to cooperate in the handover and deliver documentation. If it does not, it will have to be negotiated.
- Data ownership. Who owns the CMMS data, maintenance history and reports, and in what format they are handed over.
- Provider assets. Equipment, tools, consumables in stock, software or licences that belong to the provider and will leave with it.
- Assigned staff. Who delivers the service at each site and whether there is an obligation for the new provider to take them on (see below).
How far in advance should you start?
The practical way to work it out is backwards from the contract end date. The phases are always the same; their length depends on the size of the contract and the number of sites:
- Diagnosis. Audit of the current contract and decision between renewing, renegotiating or re-tendering.
- Specification. Scope, baseline data, KPIs, commercial model and entry and exit obligations. This is the most underestimated phase.
- Tender. Publication, site visits, clarifications, bids and bid evaluation.
- Award and notice. Notice to the outgoing provider must fall within the contractual period.
- Mobilisation. From award to the new provider’s first day of service, and then to stabilisation.
The most common mistake is to start with the tender when expiry is close. The result is a specification copied from the previous one, without the baseline data bidders need, and a mobilisation squeezed into a few weeks. If the timeline no longer works, a short extension agreed with the incumbent is usually less risky than a rushed start.
What must the outgoing provider hand over?
The outgoing provider knows the buildings best and, at the same time, has the least incentive to spend time on the exit. That is why the list of deliverables is set in writing, with format and date:
- Asset and installation register per site, with condition.
- Planned and reactive maintenance history, exported from the CMMS in a format the new provider can load.
- Statutory maintenance documentation: certificates, inspections carried out and upcoming dates.
- Open incidents, pending work and approved quotes not yet executed.
- List of subcontractors and supplies linked to the service.
- Keys, cards, access rights and user accounts for building systems.
- List of staff assigned to the service, where there is a transfer of staff.
Two practices help make it happen: keep the KPI dashboard and review meetings running until the last day, because the final months are the ones that suffer most; and write into the new contract, from the start, the exit obligations you will require from the next provider in a few years’ time. The next change of provider starts in this specification.
What about the staff?
In labour-intensive services —cleaning, security, reception, much of maintenance— a change of provider may mean the new contractor has to take on the staff who deliver the service. In Spain that obligation may come from the sector’s collective agreement or from the transfer-of-undertaking rules in Article 44 of the Workers’ Statute (Estatuto de los Trabajadores); in other countries the rules differ. Its exact scope depends on each case, so review it with employment-law advice before tendering.
The operational point is this: if staff will transfer, bidders need to know their actual terms to cost their bids. If the specification does not include them, each bidder will make its own assumption and the bids will not be comparable (how to bring them back to a common baseline is explained in how to evaluate Facility Management bids).
A hypothetical example
A company with an office network has a maintenance and cleaning contract expiring in spring, with automatic extension unless notice is given in time. In autumn, the head of Corporate Services decides to tender because complaints have multiplied. The prior audit shows two things: the provider meets the contract’s indicators, but those indicators only measure whether the task was done, not whether the user’s problem was solved; and the contract says nothing about handing over CMMS data.
The company tenders anyway, but with a different specification: outcome indicators, baseline data per site and an exit clause for the future. With the incumbent it negotiates, in exchange for being allowed to bid, a commitment to hand over historical data. If it wins again, it will do so under a contract that can finally be managed; if it loses, the new provider starts with information.
What to do on Monday morning
Open the current contract and note three dates: expiry, notice deadline and the last scope review. If a diagnosis, a specification and a tender do not fit between today and the notice deadline, you already know that the first conversation with the incumbent is about an extension, not the exit.
Once there is an award and a start date, the work becomes the transition and mobilisation plan. If you are still deciding, FM tender advisory starts exactly there (and the FAQ on Facility Management contracts answers the most common questions about duration, KPIs and exit clauses); and if you would rather talk it through first, get in touch.