In a multi-site Facility Management contract, opening, closing and changing sites is business as usual, not an exception. To avoid renegotiating the contract every time, five things need to be fixed from the tender stage: a unit price per site type and service, an add-and-remove procedure with notice periods and effective dates, a pro-rating rule for invoicing, a tolerance band for changes in the portfolio within which terms stay the same, and what happens to staff, assets and data when a site leaves the contract. Without those rules, every change becomes a negotiation with no competition, and the client starts it at a disadvantage.
Why do site additions and removals unbalance a multi-site contract?
A network of branches, stores or offices is never static. Sites open, others close, some move, change their opening hours or their floor area. If the contract was signed on a closed list of sites and a single overall price, each of those changes has to be negotiated outside the competitive process: there are no other bidders in the room any more, and the incumbent provider is the one proposing the price for the new site and the reduction for the one that closes.
The symptoms are usually the same three:
- New sites priced above the original bid. They are quoted one by one and end up more expensive than equivalent sites in the awarded offer.
- Closed sites still on the invoice. The removal is notified late, applied late, or the notice period becomes a dispute.
- A portfolio nobody can describe. Annexes, emails and change orders that are never consolidated, so after a while there is no reliable list of which sites and which services are actually under contract.
None of these is really the provider’s fault. It is a contract design problem, and it is solved before signing.
What should the contract fix from day one?
- A unit price per site type. A catalogue of site types (for example small branch, standard branch, regional office, warehouse) with a price per service and per unit: square metre, site or hour, depending on the service. When a site opens, it is classified and its price applies, with no negotiation. For this to work, unit prices must be requested in the tender and form part of the awarded bid, so they are compared alongside everything else, as explained in how to evaluate Facility Management bids.
- An add, remove and change procedure. Who can request it, through which channel, with how much notice, which document formalises it (a numbered add or remove order), what the effective date is, and how quickly the provider must have the service running at a new site. A reasonable notice period depends on the service: bringing cleaning into a small office is not the same as staffing security posts at a new site.
- A pro-rating rule. The service is invoiced from the effective date of the addition and stops being invoiced from the effective date of the removal, by day or by whatever fraction is agreed, with no minimum charges that are not written down.
- A portfolio tolerance band. A cumulative change margin, measured in number of sites or in annual value, within which unit prices hold. If the portfolio moves outside that band, a review is triggered under rules agreed in advance. The band protects both sides: the provider from a contract that empties without warning, and the client from reopening the whole contract every time a site opens.
- Site exit. What happens to the staff assigned to the site, to equipment and consumables, keys and access cards, technical maintenance records and the site’s history in the maintenance management system. The site’s data must remain the client’s.
A note on staff for international readers: in Spain, sector-wide collective agreements in services such as cleaning and private security commonly regulate the transfer of staff when the company providing the service changes, a mechanism known as subrogación, conceptually similar to TUPE in the UK. Closing a site, moving it or changing its provider can therefore have employment consequences that should be reviewed with employment counsel before the clause is drafted, not afterwards. Other countries have their own rules.
And a note on scope: all of the above refers to contracts between private companies. In Spain, changes to public-sector contracts are governed by the Public Sector Contracts Act (Ley 9/2017), which sets its own conditions and limits.
How do you define site types so that unit pricing works?
A site type is only useful if two sites of the same type cost roughly the same to serve. That means building types from the variables that actually drive service cost: floor area measured on a common basis, opening hours, how the site is used and the service level required. The baseline you need is the same one used to compare costs across a network, described in how to compare facility services costs across sites and branches.
Three practical rules:
- Few types. Just enough to keep the catalogue manageable and let every site fit without argument.
- Ranges, not named sites. Each type is defined by ranges of floor area and opening hours, not by a list of specific sites, so future sites fit too.
- Keep the unusual ones separate. Headquarters, a data centre or a large logistics warehouse do not belong in a catalogue: they are priced individually and identified as such in the contract.
What changes in an IFM contract or a contract split into lots?
In an Integrated Facility Management (IFM) contract there is one more element: the management fee. You have to decide whether it stays fixed, varies with the portfolio or moves in steps. If it is fixed and the network shrinks, the client pays for a management structure sized for a network that no longer exists; if it is fully variable, the provider cannot plan its team. Steps are usually the balance point.
In a contract split into territorial lots, the question is which lot a site belongs to when it opens in an area nobody planned for, or on the border between two lots. The rule has to be written from the start; otherwise the decision is made by whoever invoices it first.
How do you keep control of the portfolio over the life of the contract?
The tool is a live contract inventory: a single list of sites with their type, contracted services, start date, end date if any, and the price applied. The list is versioned with every add or remove order and reconciled against the invoice every month. Any site invoiced but missing from the inventory, or the other way round, is an exception to resolve.
At the contract review meeting it is worth looking at pending additions and removals and at two simple indicators: actual time to bring a new site into service against the agreed lead time, and the number of removed sites still appearing on the invoice. How to define them so they are useful is covered in how to design the KPIs of a Facility Management contract, and how they fit into the control model in Facility Management governance.
A hypothetical example
An organisation with an office network closes a group of branches and opens new ones over the course of a year. Under a closed-list contract, every opening needs a quote, which comes in above what equivalent branches pay, and several closures take months to disappear from the invoice because nobody formalised the removal. With a catalogue of site types, numbered add and remove orders and an inventory reconciled with the invoice, the same changes become administrative steps at a known price. The example is illustrative and does not describe a real case.
What to check in your current contract
- Are there unit prices per site type and service, or only an overall price?
- Is the add and remove procedure written down, with notice period, document and effective date?
- How is the invoice pro-rated when a site joins or leaves mid-month?
- Is there a portfolio tolerance band, and what happens if it is exceeded?
- What happens to staff, assets and data when a site leaves the contract?
- Does the list of contracted sites match the sites that appear on the invoice today?
If any answer is no, you are probably paying for sites you no longer have, or negotiating every opening without competition. These clauses are designed in the technical specification and fixed during the Facility Management tender; if the contract is already running, reconciling the portfolio against invoicing is one of the first checks in a Facility Management contract audit. If you would like to review it for your own site network, get in touch.