How to evaluate Facility Management bids: normalise before you score

Bids in a Facility Management tender should be evaluated in four steps, in this order: check that each bid complies with what was asked, normalise all bids to a common baseline, verify that each one is viable and only then score them against criteria fixed before the bids were opened. Scoring first and analysing later is the most common way of awarding the contract to whoever wrote the best technical proposal, not to whoever will deliver the best service.

Why can’t bids be scored as they arrive?

Because every bidder answers the specification in its own way. One includes consumables and another invoices them separately. One sizes planned preventive maintenance from each asset’s maintenance plan and another from a standard frequency. One quotes a low fixed price and an expensive schedule of rates; another does the opposite. On paper, they all comply. In practice, they are competing on different things.

If the price formula is applied directly to the total amount bid, you are comparing the price of different services. And the technical score does not correct that bias: it usually amplifies it, because the best-written proposal tends to come from the bidder with the strongest bid team, not necessarily from the one that has best understood your buildings.

Before any of that comes a decision that shapes the comparison: who was invited. How to build that list is covered in who to invite to a facilities management tender.

Step 1: does the bid comply with what was asked?

Before reading a single technical proposal, run a compliance review with three questions per bid:

  • Does it cover the full scope? Service by service and site by site. Exclusions tend to hide in footnotes to the pricing schedule or in a section called “bid assumptions”.
  • Does it follow the requested price structure? If the tender asked for a price per site per month and the bid gives a single lump sum, there is no clean way to compare it.
  • Does it add its own conditions? Different price review mechanisms, liability caps, payment terms or minimum volume commitments that the tender documents did not provide for.

Every deviation goes into a table, with its impact. Some are resolved in the clarification round; others are quantified in the next step.

Step 2: how do you normalise bids with different scopes?

Normalising means bringing every bid to the same service perimeter and the same pricing unit before comparing them. The method is simple to describe and laborious to carry out:

  1. Set the reference perimeter: the full scope of the specification, with the baseline data that was published (floor areas, assets, volumes, opening hours).
  2. For each bid, identify what falls outside that perimeter and calculate what it would cost to cover it, using the bidder’s own schedule of rates or, if there is none, a documented market reference.
  3. Add that cost to the amount bid. The result is the comparable price, and that is the figure that goes into the price formula.
  4. Review the variable items separately (reactive maintenance allowance, out-of-scope works, price indexation), projected over actual historical consumption, not over the consumption each bidder suggests.

If the specification did not set a common unit of measurement or publish baseline data, this normalisation will always involve some estimation. That is why bid evaluation really starts when the specification is written: avoiding the costliest mistakes in an FM specification is what makes bids comparable later.

If what you need to compare is not bids but the prices you already pay across different sites or branches, the method is similar and is set out in how to compare facility services costs across sites.

Step 3: how do you check that a bid is viable?

In labour-intensive services (cleaning, reception, security and much of maintenance), viability is decided in the hours. The check has three layers:

  • Resourcing. On-site hours and roles proposed per site, compared with historical data and with the other bids. A bid that proposes far fewer hours than the rest for the same scope has to explain how it will deliver: technology, reorganised shifts, a different supervision model. If it does not explain it, the saving will come out of the service.
  • Labour cost. The team the bid itself proposes, costed under the applicable collective agreement or wage regulations, including employer social charges, absenteeism and cover. If the price does not cover that cost plus a reasonable margin, the bid will not hold up over the life of the contract, whatever it promises.
  • Staff transfer. Where incumbent staff transfer to the new provider (subrogation in Spain, TUPE in the UK), check that the bid has costed them on that workforce’s real terms (grades, seniority, allowances) and not on entry-level pay rates.

In Spain, public-sector tenders are bound by article 149 of Law 9/2017 on Public Sector Contracts, which governs abnormally low tenders: the tender documents must set objective parameters to identify them, the bidder has the right to justify its bid before being excluded and, in any case, bids that breach labour obligations, including the sector collective agreements in force, are rejected. In a private tender none of this is mandatory, but the logic is the same: an unviable bid is not a saving, it is a problem postponed.

Step 4: how do you score the technical proposal without everyone getting the same mark?

The clearest symptom of a technical evaluation that is not working is that every bid ends up with almost identical scores. When that happens, price decides on its own, even if the tender says quality carries half the weight. To avoid it, the technical evaluation should score elements that can be verified and compared across bids, not the quality of the writing:

  • Resourcing per site and its justification.
  • A named management team with committed time on the contract, not generic organisation charts.
  • A transition plan with milestones, owners and dates, consistent with what the contract’s transition and mobilisation will require.
  • Proposed KPIs with their calculation formula, data source and consequence, the same logic explained in how to design the KPIs of an FM contract and applied in FM contract governance.
  • Information systems: client access to the CMMS, and ownership and exportability of the data.

Each criterion needs a written scale before the bids are opened: what earns the top score, what earns a middle score and what earns zero. And each mark needs a two- or three-line justification that points to a specific page of the bid. If someone asks in six months’ time why the winner won, the answer has to be in that document.

In the Spanish public sector, article 146 of the same law asks contracting authorities to give precedence, wherever possible, to criteria that can be assessed by formula and, in certain procedures, assigns the assessment of judgement-based criteria to a committee of experts when those criteria carry more weight than the formula-based ones. In private tenders, borrowing that discipline (criteria closed before the bids are opened, technical evaluators who do not know the prices while they score) protects the decision from last-minute pressure.

What should you ask in the clarification round?

The clarification round is not there for bidders to repeat their proposal. It is there to resolve the deviations found in steps 1 to 3 and to test what they have written. Some questions that separate bids:

  • Which named person will manage the contract, and how much of their time will it get?
  • How will you cover absences at sites with a single operative?
  • What work do you expect to invoice outside the fixed price in the first year, and at what price?
  • What will you do in the first 30 days, and what do you need from the client to do it?
  • Which KPI in the specification do you consider impossible to meet, and why?

The last one is the most useful: the bidder who answers with data is usually the one who read the specification intending to deliver it.

A hypothetical example

Three bids for a maintenance and cleaning contract across a network of offices. Bid A is the cheapest on total amount; B and C are higher. Once normalised, it turns out that A excludes cleaning consumables and sets a low threshold above which any repair is invoiced separately. Projected over the reactive maintenance history, the extra cost of those exclusions means A is no longer the cheapest. On top of that, A proposes fewer cleaning hours than B and C for the same floor area without explaining how. Compared on total amount, A was the winner; compared on a normalised basis, it was not. The example is illustrative and does not correspond to any real tender.

What to do on Monday morning

If you have bids on the table, before scoring anything build a single table: one row per bidder and one column for every exclusion or condition that was not in the specification. If that table is not empty (and it almost never is), you are not yet in a position to compare prices.

Short answers to the most common questions about award criteria are in the FAQ on Facility Management contracts; if you are still deciding whether to go to tender at all, start with changing your Facility Management provider; if the specification itself is not yet written, see how to write the technical specification for an FM contract; and a full process, from specification to award, is described in the national distribution IFM tender case study. If you are in the middle of an evaluation, FM tender advisory explains how I work on the evaluation matrix and the negotiation, and you can get in touch to review it together.

Hugo Gómez Crespo

Hugo Gómez Crespo