These are the thirty-six questions that come up most often when someone has to buy, tender, govern or audit a Facility Management contract. Each answer is direct and self-contained: it can be read on its own, without the rest of the page, and points to the content that develops it in detail. The answers are written from practice in Spain; where a point depends on Spanish law or the Spanish market, it says so.
They are grouped by the moment in which they appear: first deciding the model and choosing a provider, then going to tender, then governing the live contract, and finally auditing and adjusting it. If your question is not here, write to me and I will add it.
A. Buying FM and choosing a provider
Should I go for an IFM model with a single provider or keep several specialist providers?
An IFM model makes sense when there are many dispersed sites, the in-house FM team is small and the services are standard. A multi-vendor model makes sense when there are few, concentrated sites, a highly specialised critical service, or an in-house team with the technical judgement to coordinate. The deciding question is not price: it is how much management capacity you have in-house.
Covered in more depth in Integrated Facility Management (IFM) model.
What do I lose if I contract all my services with a single facility management provider?
Four things: visibility of the price of each service, which disappears into an aggregate amount with a management fee; the ability to benchmark each service against the market; the freedom to replace only the piece that fails; and specialisation, because the most technically demanding service tends to be levelled down. All four can be mitigated in the contract if they are understood before signing it.
Covered in more depth in Integrated Facility Management (IFM) model.
From how many sites or what level of spend does an integrated FM contract pay off?
There is no universal threshold, but there are two reliable signals: when coordinating providers consumes more internal time than supervising the service, and when the volume is attractive to solvent integrated providers, which in Spain usually means above roughly half a million euros a year. Below that, the management fee is rarely justified.
Covered in more depth in Integrated Facility Management (IFM) model.
What is the real difference between buying facility services and buying facility management?
Facility services means buying deliverables: cleaning, maintenance, security, each on its own. Facility management means buying the management of those deliverables: an operating model, a single counterpart accountable for the whole, a set of indicators and a coordination layer. The difference is not who does the cleaning; it is who answers for the whole thing working.
Covered in more depth in Facility Management consulting.
What should I ask a facility management provider before contracting them?
Five questions that separate a provider who has read your specification from one who has recycled its previous bid: which part of the service it subcontracts and to whom; which named team will manage your contract; exactly how it calculates each indicator it offers; what happens on the day it fails to perform; and what it hands over if you ever decide to leave.
Covered in more depth in FM tender advisory.
What must a facility management contract include so that it does not leave me exposed?
Six pieces: scope with its explicit exclusions, service levels with a calculation formula, a progressive and capped penalty regime, reporting obligations and access to data, a transition plan with milestones, and exit clauses that oblige the provider to hand over the asset inventory, history and CMMS data in a usable format. Without the last one, lock-in is real even if the contract is annual.
Covered in more depth in FM tender advisory.
How long should a facility management contract last?
Three to five years for an integrated contract that requires investment in transition, and one to three years for standard services with no significant mobilisation. What matters is not the length but the exit points: an annual review of the indicator set, and a right to terminate for repeated underperformance defined by an objective threshold, not by a subjective assessment.
Covered in more depth in FM tender advisory.
Should I outsource general services or keep them in-house?
It depends on whether the service differentiates your business or is a cost to be managed. What outsources well is what can be standardised, what needs geographical coverage and what requires a scale you do not have. What is best retained is what touches the customer experience, what involves sensitive information and, always, the capacity to decide and to control.
Covered in more depth in Facility Management consulting.
B. Going to tender
How do I prepare a technical specification for a cleaning and maintenance service?
With nine pieces: real baseline data, scope per service with its exclusions, service levels with formulas, a penalty regime, reporting obligations, a transition plan, systems and data-ownership requirements, exit conditions and award criteria. Publishing the real asset inventory and volumes is what prevents most inflated bids, and it is what is most often neglected.
Covered in more depth in FM tender advisory.
How much should price weigh in an FM tender?
Between 40% and 50%, leaving the remaining 50–60% to the technical evaluation. But the split matters less than this: if the technical criteria are so generic that every bidder gets almost the same score, the real weight of price is 100%, whatever the tender documents say.
Covered in more depth in FM tender advisory.
How do I design award criteria that do not simply reward the lowest price?
By making the technical criteria genuinely discriminate: score verifiable, comparable elements — proposed staffing per site, the named profile of the management team, a transition plan with milestones, the formulas behind the indicators — rather than generic method statements. And score the schedule of unit rates for out-of-scope work, which is where whatever was conceded on the fixed price gets recovered.
Covered in more depth in FM tender advisory.
How do I spot an abnormally low bid for a services contract?
Compare the bid with the minimum labour cost, under the applicable collective agreement, of the team the bid itself proposes: if it does not cover wages, social security contributions and absence cover, it is not viable, whatever it promises. In the Spanish public sector, Article 149 of Law 9/2017 on Public Sector Contracts sets out the procedure for the bidder to justify the price and allows the bid to be excluded if it is not justified.
Covered in more depth in FM tender advisory.
How do I compare FM bids that include different scopes and are not comparable?
Normalise them before scoring: set a common unit, bring each bid to that unit and value separately the exclusions each one introduces, quantifying what it would cost to cover them. If the tender documents did not fix the unit of measure and the baseline data, this comparison will always be partly subjective. The full four-step method is in how to evaluate Facility Management bids.
Covered in more depth in FM tender advisory.
What is the difference between the technical specification and the commercial or administrative terms?
The technical specification defines what is being bought: scope, service levels, resources and how they are measured. The administrative terms define how it is bought and under what rules: procedure, required solvency, deadlines, award criteria and their weighting, guarantees, invoicing and termination. In Spanish public procurement these are two separate documents (PPT and PCAP). A good specification inside badly built administrative terms cannot be awarded well.
Covered in more depth in FM tender advisory.
When do I use an RFI, an RFP or an RFQ to buy services?
An RFI is for understanding the market when you do not yet know which model you want: you ask for information, not price. An RFP is used when the scope is defined but the solution is not, and you ask for a technical and commercial proposal. An RFQ only works when the specification is closed and the only variable is price.
Covered in more depth in FM tender advisory. How to use an RFI to decide who to invite: the bidder shortlist.
What do I do if my services tender receives no bids or only one?
Before repeating it, find out why. The four usual causes: a response period that is too short, baseline data insufficient to price without risk, commercial or penalty terms perceived as unacceptable, and a poorly chosen invitation list. Repeating the same specification with more invited companies usually produces the same result.
Covered in more depth in FM tender advisory.
How do I include ESG criteria in a services tender so they do not stay on paper?
By turning them into measurable obligations with a contractual consequence, not into statements that earn points. A useful ESG criterion has an indicator, a data source and a frequency: energy consumption reported monthly, the percentage of waste segregated with a certificate from the authorised waste manager, or staff training in verified hours. A sustainability commitment without an indicator is a nice essay.
Covered in more depth in FM tender advisory.
Should I split an FM contract into lots or tender it as a whole?
Lots increase competition and let specialists in, at the cost of more internal coordination. A single contract simplifies management and concentrates risk. The practical rule: split when a service has its own mature market — security and catering almost always do — and group what benefits from a single plan.
Covered in more depth in FM tender advisory.
C. Controlling the provider and governing the contract
How many KPIs should a Facility Management contract have?
Between 8 and 12 contractual indicators, meaning those that trigger a financial consequence. The rest are management indicators: useful in the review meeting, with no effect on the invoice. When a contract exceeds thirty contractual indicators, the usual effect is not more control but less: nobody reviews them and the provider optimises whatever is measured.
Covered in more depth in how to design the KPIs of an FM contract and FM contract governance.
Which KPIs should I require from my facility management provider?
One or two per family: availability of critical installations, response and resolution times segmented by criticality, compliance with the planned preventive maintenance programme, statutory and regulatory compliance, user satisfaction with an adequate sample, and financial discipline. That covers the contract in 8–12 indicators without ending up with an ungovernable scorecard.
Covered in more depth in FM contract governance and in the governance and KPI framework case study.
What should a Facility Management SLA include?
Five elements for each committed level: a definition of the service and its criticality, an indicator with its calculation formula, a target threshold and a penalty threshold, a measurement window and exclusions, and a financial consequence. An SLA without defined exclusions gets renegotiated every month; one without a calculation formula can never be applied.
Covered in more depth in FM contract governance.
What penalties can I apply if my provider misses the service level?
Whatever is written into the contract, with three conditions for them to work: a progressive scale rather than a single step, a contractual cap — without a cap no solvent provider signs — and automatic application against the monthly valuation. If applying a penalty requires a discretionary decision by the client every month, in practice it will not be applied.
Covered in more depth in FM contract governance.
How should I structure the governance meetings of a services contract?
On three levels: an operational meeting, weekly or fortnightly, for incidents and planning; a tactical monthly meeting for indicators, deviations and the action plan; and a strategic quarterly meeting for trends, penalties, scope changes and renewal. Merging the tactical and strategic levels is the most common mistake: operational urgency always eats the deeper conversation.
Covered in more depth in FM contract governance.
What information should my provider report to me every month?
Five blocks and no more: performance against each indicator with the raw data behind it, open and recurring incidents by asset, delivery of the planned preventive maintenance programme, financial position against budget with detail of out-of-scope work, and risks or decisions that need the client. A forty-page report that does not allow anyone to decide anything is a failed report.
Covered in more depth in FM contract governance.
How do I build a facility management dashboard?
Start from the decisions, not from the data available. First define which decisions are taken in each meeting, then which indicator informs each decision, and only then where the data comes from. The resulting dashboard fits on one screen, distinguishes contractual indicators from management indicators and shows the trend, not just this month’s value.
Covered in more depth in FM contract governance.
Why does my provider meet every KPI while the service keeps getting worse?
Because the indicators measure activity, not outcome. The typical case is closing incidents on time without measuring recurrence: a unit that breaks down four times a month produces four impeccable closures and a user without air conditioning. The fix fits in one line: add reopening or recurrence on the same asset, with its own threshold.
Covered in more depth in FM contract governance.
How do I plan the transition when I change facility management provider?
With a 90-day plan with contractual milestones: handover of asset information, transfer of staff where it applies (in Spain, staff transfer is often required by the sector collective agreement), go-live of the management system, onboarding of subcontractors, first measurement of indicators and first review meeting. If the tender did not set that plan and its penalties, nobody is accountable for the three months in which the service degrades most.
Covered in more depth in transition and mobilisation and in Changing your Facility Management provider.
Which team should I keep in-house after outsourcing general services?
Four capabilities, even if they are few people: someone who decides and approves spend, someone who controls the contract and the indicators, someone who retains technical knowledge of the critical assets, and someone who is the face to the internal user. You outsource execution; you never outsource the capacity to decide or the capacity to check.
Covered in more depth in FM contract governance.
What do I do when a facility management contract is deteriorating?
Before terminating, measure. A recovery plan starts by documenting the failures with evidence for two or three months, takes them to the strategic meeting with an explicit deadline for correction and comes with an action plan with named owners. Terminating without that record leaves the client with no negotiating position and the full cost of transition.
Covered in more depth in FM contract governance and in Changing your Facility Management provider.
D. Auditing, measuring and saving
How often should a Facility Management contract be audited?
In depth every two or three years, and always once between six and twelve months before expiry, so that the findings feed the next tender. In contracts with active governance — measured indicators, minuted meetings and verified reporting — a formal audit is less urgent, because that control is already exercised continuously.
Covered in more depth in FM contract audit and in the FM contract audit checklist.
How do I know whether I am overpaying for my cleaning or maintenance contract?
Seven signs: a contract more than three years old that has not been reviewed, a variable invoice nobody can explain, out-of-scope work above 15–20% of the base contract, no penalty ever applied, unverified reporting, automatic inflation indexation without a scope review, and no idea of the cost per m² or per site. With three or more, there is room to improve.
Covered in more depth in FM contract audit and in the FM contract audit checklist.
How is a facility management contract audited?
By comparing three realities that almost never match: what the contract says, what is invoiced and what is actually delivered. The findings are organised into six dimensions — scope, price, service, control, risk and governance — so they can be prioritised by financial impact instead of piling up a list of unconnected complaints.
Explained step by step in how to audit a Facility Management contract, and as a service in FM contract audit.
How much should facility management cost per m² of office space?
In Spain there is currently no reliable public benchmark of FM cost per m²: the figures in circulation come from commercial reports with unpublished samples or from English-speaking markets. Any useful reference has to normalise scope, operating hours, criticality and service level, because without that two identical buildings can show costs that differ by more than double.
Covered in more depth in FM contract audit.
How do I detect inefficiencies and cost overruns in my services contracts?
By cross-checking invoicing against the contract and against the service delivered. The most frequent leaks: services invoiced at closed sites, frequencies designed for a previous occupancy, different unit rates for the same work depending on the area, inflation increases applied to the total instead of the labour component, and recurring work invoiced as out-of-scope year after year.
Covered in more depth in FM contract audit.
How do I reduce facility management costs without lowering the service level?
In this order: adjust the scope to actual occupancy and use, bring into the contract the recurring work that is currently paid as out-of-scope, correct inconsistent unit rates, re-plan preventive maintenance by criticality rather than habit, and review the price-adjustment formula. Cutting frequencies comes last, and it is usually the first thing proposed.
Covered in more depth in FM contract audit.
What is the difference between a CMMS, a CAFM and an IWMS, and which one do I need?
A CMMS manages maintenance: assets, work orders and preventive maintenance. A CAFM adds the management of space and building services. An IWMS also integrates real estate, contracts and sustainability in a single corporate platform. Most organisations need a well-implemented CMMS, not a badly used IWMS. (In Spanish the CMMS is called GMAO.)
Covered in more depth in Facility Management consulting.
When a question becomes a project
Most of these questions appear at a specific moment: a contract about to expire, a tender being drafted, a provider whose numbers look fine while users complain. If you are at one of those moments, tender advisory, contract governance and an independent contract audit are where the work usually starts. If you would rather talk it through first, get in touch.